Consider the project with the following estimates for activity times and precedence relationships:
(a)What is the expected duration of the project?
(b)What is the project variance?
(c)If the deadline of the project is 25 days, what is the probability of finishing the project on time?
Correct Answer:

Verified
(a)23 (b)3...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q132: Given an activity's optimistic, most likely, and
Q133: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Figure 11-1
Q134: Table 11-3<br> <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5481/.jpg" alt="Table 11-3
Q135: In CPM, crashing an activity that is
Q136: Given an activity's optimistic, most likely, and
Q137: Activity C of a project has a
Q139: A PERT/CPM network is a graphical display
Q140: Table 11-8<br>A mad scientist has identified the
Q141: Given the assumptions in PERT, the probability
Q142: The identification of the project activities and