Essay
Consider the tasks, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow. (a) What is the expected duration of the project?
(b) What is the probability of completion of the project before week 42?
Correct Answer:

Verified
Correct Answer:
Verified
Q12: CPM stands for<br>A)critical path management.<br>B)critical project management.<br>C)critical
Q62: Slack time in a network is the<br>A)amount
Q73: Given an activity's optimistic,most likely,and pessimistic time
Q85: With PERT, we are able to calculate
Q89: PERT was developed for a project for
Q108: Given an activity's optimistic,most likely,and pessimistic time
Q111: Table 12-4<br>The following represents a project with
Q113: Development of a new deluxe version of
Q115: Table 12-1<br>The following represents a project with
Q117: Table 12-1<br>The following represents a project with