Multiple Choice
In PERT,we assume that
A) the times to complete individual activities are known with certainty.
B) all activities are carried out by staff from our own organization.
C) the total cost of a project is independent of the time to complete the project.
D) the total time to complete all activities on the critical path is described by a normal distribution.
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q39: PERT assumes that the total completion time
Q40: Development of a new deluxe version of
Q41: Consider the following project schedule: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg"
Q43: Your company is considering submitting a bid
Q45: The expected completion time and variance of
Q46: Consider a project that has an expected
Q47: The crash time of an activity represents<br>A)the
Q48: Table 11-2<br>The following represents a project with
Q49: Figure 11-1 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Figure 11-1
Q131: Given the variability of the activity completion