Multiple Choice
Given an activity's optimistic,most likely,and pessimistic time estimates of 4,6,and 14 days respectively,compute the PERT expected activity time for this activity.
A) 8
B) 6
C) 7
D) 9
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q68: Given an activity's optimistic,most likely,and pessimistic time
Q71: In PERT,the variance in completion time is
Q72: Which of the following statements about project
Q74: Given an activity's optimistic,most likely,and pessimistic time
Q75: What is the minimum possible time required
Q76: Managers use the network analysis of PERT
Q78: Given the following small project,the critical path
Q105: PERT and CPM are quantitative analysis tools
Q137: Activity C of a project has a
Q139: A PERT/CPM network is a graphical display