menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Quantitative Analysis for Management Study Set 2
  4. Exam
    Exam 11: Project Management
  5. Question
    Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 4,6,and
Solved

Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 4,6,and

Question 73

Question 73

Multiple Choice

Given an activity's optimistic,most likely,and pessimistic time estimates of 4,6,and 14 days respectively,compute the PERT expected activity time for this activity.


A) 8
B) 6
C) 7
D) 9
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q68: Given an activity's optimistic,most likely,and pessimistic time

Q71: In PERT,the variance in completion time is

Q72: Which of the following statements about project

Q74: Given an activity's optimistic,most likely,and pessimistic time

Q75: What is the minimum possible time required

Q76: Managers use the network analysis of PERT

Q78: Given the following small project,the critical path

Q105: PERT and CPM are quantitative analysis tools

Q137: Activity C of a project has a

Q139: A PERT/CPM network is a graphical display

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines