Multiple Choice
Total slack is calculated for each of the activities by finding the difference between
A) the ES of the activity and the LF of the activity or the difference between the EF and LS of the activity.
B) the EF of the activity and the LS of the activity or the difference between the ES and LF of the activity.
C) the EF of the activity and the LF of the activity or the difference between the ES and LS of the activity.
D) the ES of the activity and the LF of the activity or the difference between the ES and LF of the activity.
Correct Answer:

Verified
Correct Answer:
Verified
Q2: If the project needs accelerated, efforts should
Q3: The _ involves regularly gathering data on
Q4: The key to effective project control is
Q5: The earliest start time for an activity
Q6: Having the person who will be responsible
Q7: Latest finish time (LF)is the latest time
Q8: If the total slack for a project
Q9: It is important to know what types
Q10: Throughout the performance of the project, some
Q11: The development team develops, delivers, and demonstrates