Schedule Updates of the Project Using Actual Finish Times

Question 25

Multiple Choice

Schedule updates of the project using actual finish times


A) are calculated forwards and backwards in the project schedule as when planning the project schedule.
B) show how much money has been expended on the project.
C) identify where there are too many resources on the project.
D) show where there are increased risks for the project.

Correct Answer: