    In PERT,the Variance in Completion Time Is Equal to the Variance
Solved

In PERT,the Variance in Completion Time Is Equal to the Variance

Question 71

Question 71

True/False

In PERT,the variance in completion time is equal to the variance of the most time consuming activity on the critical path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q67: Table 11-6 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-6

Q68: Given an activity's optimistic,most likely,and pessimistic time

Q72: Which of the following statements about project

Q73: Given an activity's optimistic,most likely,and pessimistic time

Q74: Given an activity's optimistic,most likely,and pessimistic time

Q75: What is the minimum possible time required

Q76: Managers use the network analysis of PERT

Q105: PERT and CPM are quantitative analysis tools

Q114: One PERT/COST assumption is that money is

Q137: Activity C of a project has a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines