Which of the following statements about project crashing is false?
A) The crash cost is greater than or equal to the normal cost of an activity.
B) The crash time is less than or equal to the normal time to complete an activity.
C) Reducing the time of an activity on the critical path automatically reduces total project duration.
D) It may not be possible to crash a particular activity.
E) Crashing may not lead to an overall reduction in costs for the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q67: Table 11-6 <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB2950/.jpg" alt="Table 11-6
Q68: Given an activity's optimistic,most likely,and pessimistic time
Q71: In PERT,the variance in completion time is
Q73: Given an activity's optimistic,most likely,and pessimistic time
Q74: Given an activity's optimistic,most likely,and pessimistic time
Q75: What is the minimum possible time required
Q76: Managers use the network analysis of PERT
Q105: PERT and CPM are quantitative analysis tools
Q137: Activity C of a project has a
Q139: A PERT/CPM network is a graphical display