menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 11: Critical Chain Project Scheduling
  5. Question
    A System-Wide Constraint Is Called A(n)
Solved

A System-Wide Constraint Is Called A(n)

Question 71

Question 71

Multiple Choice

A system-wide constraint is called a(n) :


A) rope.
B) resource.
C) drum.
D) chain.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: Drum buffers are:<br>A)a safety margin separating different

Q16: If a project activity experiences negative variation:<br>A)the

Q28: Create and solve an example of at

Q34: In order to resolve a resource conflict,it

Q54: _ is variation that is a fact

Q66: Once the organization elevates its constraint,its system

Q67: A project consists of three activities with

Q82: Project managers often add a(n)_ to individual

Q92: In order to estimate completion of a

Q93: All five members of a project team

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines