menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 11: Critical Chain Project Scheduling
  5. Question
    A Project Consists of Three Activities with Information as Shown
Solved

A Project Consists of Three Activities with Information as Shown

Question 67

Question 67

Multiple Choice

A project consists of three activities with information as shown in the table. What is the overall variance of the project? A project consists of three activities with information as shown in the table. What is the overall variance of the project?   A)  18 B)  8 C)  2.82 D)  5.56


A) 18
B) 8
C) 2.82
D) 5.56

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: Drum buffers are:<br>A)a safety margin separating different

Q16: If a project activity experiences negative variation:<br>A)the

Q27: In classic project management,activity durations are estimated

Q28: Create and solve an example of at

Q65: A project is represented by the activity

Q71: A system-wide constraint is called a(n):<br>A) rope.<br>B)

Q75: Which statement about critical chain project management

Q88: What is the difference between common cause

Q92: In order to estimate completion of a

Q93: All five members of a project team

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines