A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below: A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below:   What is the expected total time for the project? A) 7.33 days B) 9.00 days C) 10 days D) 12.67 days What is the expected total time for the project?


A) 7.33 days
B) 9.00 days
C) 10 days
D) 12.67 days