Multiple Choice
If a project path has an expected duration of 10 days and a standard deviation of three days,what is the probability that the path will be completed in 13 days or less?
A) 50 percent
B) 33 percent
C) 75 percent
D) 84 percent
Correct Answer:

Verified
Correct Answer: