Solved

Using the Critical Path Method, the Normal Time to Complete

Question 12

True/False

Using the Critical Path Method, the normal time to complete activity D is 10 weeks, and its normal cost is $500.Under maximum crashing, activity D can be completed is 4 weeks for $2,300.Therefore, if $1,100 is spent on activity D, its completion time will be 6 weeks.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions