In PERT, the Acceptance of a Beta Distribution for Activity

Question 16

True/False

In PERT, the acceptance of a Beta distribution for activity completion times and the presence of a sufficient number of activities, lead to the assumption of a normal distribution of possible completion times for the overall project.