Multiple Choice
Typically, the first step in project scheduling is the construction of a:
A) Gantt chart.
B) Critical path chart.
C) PERT chart.
D) set of precedence relationships between the activities.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q6: Consider the following information for the
Q7: In using PERT/CPM, why does management need
Q8: Overall project completion time will not be
Q9: Discuss the assumptions required for determining the
Q10: Using PERT, we have determined the
Q12: Using the Critical Path Method, the normal
Q13: The earliest start time (ES) of an
Q14: Activity C is an immediate predecessor of
Q15: In the critical path method (CPM), crashing
Q16: In PERT, the acceptance of a Beta