The Earliest Start Time (ES) of an Activity

Question 13

Multiple Choice

The earliest start time (ES) of an activity:


A) equals its earliest finish time (EF) minus task time.
B) equals the minimum earliest finish time (EF) of all immediate predecessors.
C) equals the latest start time (LS) for non-critical activities.
D) may not be the same for two or more activities.