Multiple Choice
Activity C is an immediate predecessor of activity G.Both activities have 4 hours of slack time.If both activities are delayed 3 hours, and these are the only delays, the overall effect of these delays is to delay the minimum project completion time by:
A) 0 hours.
B) 2 hours.
C) 6 hours.
D) The overall delay cannot be determined with only this information.
Correct Answer:

Verified
Correct Answer:
Verified