    The Critical Path
Solved

The Critical Path

Question 4

Question 4

Multiple Choice

The critical path:


A) is the shortest path through the network.
B) is necessarily unique.
C) Is defined by activities with zero slack.
D) Shows, by elimination, which activities management can safely ignore.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: PERT (Program Evaluation and Review Technique) generally

Q2: Which of the following is true?<br>A)PERT gives

Q3: When attempting to use PERT methodology, how

Q5: For an activity, an engineer estimatesa (optimistic

Q6: Consider the following information for the

Q7: In using PERT/CPM, why does management need

Q8: Overall project completion time will not be

Q9: Discuss the assumptions required for determining the

Q10: Using PERT, we have determined the

Q11: Typically, the first step in project scheduling

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines