Essay
For an activity, an engineer estimatesa (optimistic time) = 4
b (pessimistic time) = 11
m (most likely time) = 6
What is the mean for this activity? The variance?
Correct Answer:

Verified
(
= (a + b + 4m)/6 = 6.5