Solved

Consider the Following Information for the Activities Comprising a Small

Question 6

Essay

Consider the following information for the activities comprising a small construction project which is scheduled to complete in 26 days.(Costs are in $1000's.)
 Normal  Schedule Crash Schedule  Activity  Slack  Time  Cost  Time  Cost  M 0710419 II 25656 O 047212 P 059313 Q 22516 R 04949 S 0612515\begin{array}{cccccc}&&\text { Normal }&\text { Schedule}&\text { Crash}&\text { Schedule }\\\text { Activity } & \text { Slack } & \text { Time } & \text { Cost } & \text { Time } & \text { Cost } \\\text { M } & 0 & 7 & 10 & 4 & 19 \\\text { II } & 2 & 5 & 6 & 5 & 6 \\\text { O } & 0 & 4 & 7 & 2 & 12 \\\text { P } & 0 & 5 & 9 & 3 & 13 \\\text { Q } & 2 & 2 & 5 & 1 & 6 \\\text { R } & 0 & 4 & 9 & 4 & 9 \\\text { S } & 0 & 6 & 12 & 5 & 15\end{array} A.If the project must be completed in 25 days, which activity should be accelerated? Why?
B.Will the critical path be altered?
C.What is the total estimated cost of the project on the accelerated 25 day schedule?

Correct Answer:

verifed

Verified

A.
(Activity crash costs per day: M = 3....

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions