PERT (Program Evaluation and Review Technique) Generally Treats Activity Completion

Question 1

Multiple Choice

PERT (Program Evaluation and Review Technique) generally treats activity completion times as probabilistic and:


A) is used to construct a Gantt chart.
B) is used to determine the probability that a project will be complete within a given time frame.
C) can be used to determine the exact completion time of an activity.
D) can be used to determine the exact completion time of a project.

Correct Answer:

verifed