Review the following schedule for a small project involving only two activities:
At the end of week two, progress information for Tasks A and B is as follows:
What can we conclude about the project at the end of week two?
A) The critical path is behind schedule
B) Time estimate at completion EAC time) ) = 5.625 months
C) EAC cost) = $8,000
D) CV% = -11.11%
E) A and D only
F) All of the above
Correct Answer:

Verified
Correct Answer:
Verified