Multiple Choice
What are possible values for earned value EV) , planned value PV) , and actual cost AC) if a project has an SPI of 0.5 and a CPI of 2.0?
A) EV = $30,000, PV = $60,000, AC = $15,000
B) EV = $60,000, PV = $30,000, AC = $15,000
C) EV = $15,000, PV = $30,000, AC = $60,000
D) EV = $60,000, PV = $15,000, AC = $30,000
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q6: Given the following information at week 12
Q7: A project task is scheduled to begin
Q8: What is the difference between planned value
Q9: Given the following information about a project:<br>EV
Q10: Given the following information about a project:<br>EV
Q11: Which of the following is/are sources of
Q12: Review the following schedule for a
Q14: Which of the following project monitoring tools
Q15: Which of the following offers the best
Q16: Given the following information about a project