Solved

-Resource Levelling, or Smoothing, Levels the Resources So That

Question 19

Multiple Choice

  -Resource levelling, or smoothing, levels the resources so that A) an equal number of resources is assigned to each task. B) an equal number of tasks are completed each day by the resources on the project. C) they are applied as uniformly as possible without extending the project schedule beyond the required completion time. D) the costs for the resources are as even as possible across the project.
-Resource levelling, or smoothing, levels the resources so that


A) an equal number of resources is assigned to each task.
B) an equal number of tasks are completed each day by the resources on the project.
C) they are applied as uniformly as possible without extending the project schedule beyond the required completion time.
D) the costs for the resources are as even as possible across the project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions