When Estimating the Types and Quantities of Resources Required for Each

Question 89

Multiple Choice

When estimating the types and quantities of resources required for each specific activity, it is valuable to involve a person who


A) is hired by the customer to be a consultant regardless of experience on the type of project.
B) has expertise or experience with the activity to help make the estimate.
C) has experience negotiating contracts.
D) has the most experience using a project management information system.

Correct Answer: