The Project Control Process Involves All of the Following Except

Question 33

Multiple Choice

The project control process involves all of the following except


A) regularly gathering data on project performance.
B) comparing actual performance to planned performance.
C) taking corrective action immediately if actual performance is behind planned performance.
D) having social gatherings with the project team.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge