Multiple Choice
At a project's completion, a project manager's final task is to:
A) write team member evaluations.
B) finish administrative tasks.
C) prepare a project evaluation.
D) hold a formal project closure meeting with the sponsor and stakeholders.
E) prepare a project closure document, and send this to the sponsor and stakeholders after the project closure meeting.