Solved

The Project Team Has Identified All the Tasks Needed to Create

Question 36

Multiple Choice

The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?


A) Identify task relationships.
B) Put the resources on tasks.
C) Set the quality gates.
D) Estimate the work package.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions