Multiple Choice
The government wants to start a project that will launch a satellite but lacks the appropriate SMEs. Which of the following would be BEST to solicit vendors?
A) LOI
B) RFQ
C) RFI
D) SOW
Correct Answer:

Verified
Correct Answer:
Verified