Question 4

Multiple Choice

A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered. Which of the following are MOST likely missing from the project? (Choose two.)


A) Project charter
B) Organizational chart
C) Scope document
D) Status report
E) Business case
F) Project plan

Correct Answer: