Multiple Choice
A project manager is working on a project, which needs to be delivered within six months. The project sponsor has made it known that the six months is non-negotiable and additional funding can be provided, if required. The project is in the fifth month, and testing is ongoing. The project team has identified a major defect that will take up to one month to rectify. Which of the following is the BEST action for the project manager to take to ensure the project finishes as planned?
A) Obtain additional resources to crash the timelines.
B) Continue the project as is and communicate the imminent one-month delay to the sponsor.
C) Fast-track non-critical-path activities.
D) Deliver the products to meet the timelines and create an additional phase to address issues.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Which of the following are the BEST
Q3: Which of the following charts is a
Q4: A project team is not delivering their
Q5: A PM has a complex project that
Q6: During the testing phase, a team member
Q7: Two highly skilled resources, who are currently
Q8: The key stakeholders have reported the project
Q9: The business stakeholder has been engaged late
Q10: Which of the following is a component
Q11: A project's stakeholders have not been informed