Essay
The Following Questions adapted from tutorial material of H Steyn Ed., Project Management -A Multi-disciplinary Approach (Pretoria: FPM Publishing, 2003). Reprinted with permission.
-Consider the schedule below:
RB = Resource Buffer
FB = Feeding Buffer
PB = Project Buffer
The letters A, B, C, D and E represent the resources needed to do the indicated activities.
(a) Show the critical chain on the sketch above.
(b) Why is there no resource buffer (RB) before the activity to be performed by A?
(c) Why is there no resource buffer before the second task to be performed by resource B?
(d) Would the 6-day duration shown for the activity to be performed by A be a pessimistic or a realistic value?
Correct Answer:

Verified
Correct Answer:
Verified
Q7: To reduce the duration of a project
Q8: Statement: In the critical path method (CPM),
Q9: Statement: It is relatively easy to level
Q10: To find the shortest possible project duration
Q11: Statement: Although the times used in PERT
Q13: An approach to accelerate a project by
Q14: Statement: Indirect costs include administrative, overhead, and
Q15: Which statement is correct. The critical chain
Q16: The Following Questions adapted from tutorial
Q17: Statement: PERT requires three time estimates for