Multiple Choice
Which statement is correct. The critical chain method:
A) helps planners to estimate the duration of activities more accurately.
B) stresses that, in order to finish the project on the project deadline (due date) , all critical activities must be finished by their individual deadlines (due dates) .
C) forces a person working on an activity to commit to when he/she will finish the work.
D) ensures that sufficient contingency reserve is built into the schedule of each individual activity.
E) None of the above is correct.
Correct Answer:

Verified
Correct Answer:
Verified
Q10: To find the shortest possible project duration
Q11: Statement: Although the times used in PERT
Q12: The Following Questions adapted from tutorial material
Q13: An approach to accelerate a project by
Q14: Statement: Indirect costs include administrative, overhead, and
Q16: The Following Questions adapted from tutorial
Q17: Statement: PERT requires three time estimates for
Q18: Use the following network diagram and
Q19: Statement: A "resource loading" chart shows the
Q20: Which statement is correct: In the CPM,