Multiple Choice
An approach to accelerate a project by simply eliminating discretionary dependencies is called:
A) Crashing
B) Concurrent engineering
C) Critical chain scheduling
D) Fast tracking
E) PERT/CPM
Correct Answer:

Verified
Correct Answer:
Verified