Multiple Choice
Which statement is correct: In the CPM, as the duration of a project is decreased, usually:
A) so are both its direct and indirect costs
B) direct costs increase, but indirect costs decrease
C) both direct and indirect costs increase
D) direct costs decrease, indirect costs increase
Correct Answer:

Verified
Correct Answer:
Verified
Q15: Which statement is correct. The critical chain
Q16: The Following Questions adapted from tutorial
Q17: Statement: PERT requires three time estimates for
Q18: Use the following network diagram and
Q19: Statement: A "resource loading" chart shows the
Q21: Statement: In PERT, the mean (expected) time
Q22: Contingencies should be built in at the
Q23: If the project completion has a distribution
Q24: A project cannot have more than one
Q25: The Following Questions adapted from tutorial