Which Statement Is Correct: in the CPM, as the Duration

Question 20

Multiple Choice

Which statement is correct: In the CPM, as the duration of a project is decreased, usually:


A) so are both its direct and indirect costs
B) direct costs increase, but indirect costs decrease
C) both direct and indirect costs increase
D) direct costs decrease, indirect costs increase

Correct Answer: