Short Answer
The Following Questions adapted from tutorial material of H Steyn Ed., Project Management -A Multi-disciplinary Approach (Pretoria: FPM Publishing, 2003). Reprinted with permission.
-Put checks in the appropriate boxes in the table below.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Statement: A "resource loading" chart shows the
Q20: Which statement is correct: In the CPM,
Q21: Statement: In PERT, the mean (expected) time
Q22: Contingencies should be built in at the
Q23: If the project completion has a distribution
Q24: A project cannot have more than one
Q26: When there are multiple critical paths and
Q27: Which statement is incorrect:<br>A) Unlike the critical
Q28: The following buffer enables the project manager
Q29: Statement: In resource loading, the project schedule