menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management for Engineering
  4. Exam
    Exam 8: Advanced Project Network Analysis and Scheduling
  5. Question
    Statement: in PERT, the Mean (Expected) Time for Each Activity
Solved

Statement: in PERT, the Mean (Expected) Time for Each Activity

Question 21

Question 21

True/False

Statement: In PERT, the mean (expected) time for each activity is determined by using a formula that gives the greatest weight to the "optimistic" time estimate.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q16: The Following Questions adapted from tutorial

Q17: Statement: PERT requires three time estimates for

Q18: Use the following network diagram and

Q19: Statement: A "resource loading" chart shows the

Q20: Which statement is correct: In the CPM,

Q22: Contingencies should be built in at the

Q23: If the project completion has a distribution

Q24: A project cannot have more than one

Q25: The Following Questions adapted from tutorial

Q26: When there are multiple critical paths and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines