Multiple Choice
If the project completion has a distribution with Te = 15 weeks and Vp = 9, what is the probability that the project will be completed in less than 18 weeks? To answer this, the correct z value is:
A) 0.333
B) 1
C) -1
D) none of these
Correct Answer:

Verified
Correct Answer:
Verified