Multiple Choice
When there are multiple critical paths and the project duration must be reduced, it is necessary to make reductions:
A) on whichever critical path affords the smallest cost increase
B) on whichever non-critical path affords the smallest cost increase
C) that will shorten all of the critical paths
D) that will shorten all of the non-critical paths
Correct Answer:

Verified
Correct Answer:
Verified