Multiple Choice
The criticism of network techniques that some project work cannot be known beforehand can be somewhat overcome by:
A) drawing a Gantt chart.
B) using the AON method.
C) never planning project activities in detail.
D) using a suitable computer system.
E) breaking the project down into phases and planning only the imminent phase in detail.
Correct Answer:

Verified
Correct Answer:
Verified