Multiple Choice
Resource leveling:
A) makes use of float (slack) to move activities to to time slots other than the "as early as possible" dates.
B) makes the workload on resources more evenly distributed.
C) can potentially turn non-critical activities into critical ones.
D) all of the above.
E) (a) and (b) above.
Correct Answer:

Verified
Correct Answer:
Verified