Multiple Choice
Which 3 products are created once the authority to initiate the project has been received?
A) Risk Management Strategy, Quality Management Strategy, Communication Management Strategy
B) Project Plan, Configuration Management Strategy, Quality Management Strategy
C) Project Plan, Risk Management Strategy, Quality Management Strategy
D) Risk Management Strategy, Quality Management Strategy, Configuration Management Strategy
Correct Answer:

Verified
Correct Answer:
Verified
Q89: When a work package is returned, which
Q90: James Kirk is the project manager for
Q91: Which of the following is NOT a
Q92: Which role(s) has/have ultimate authority on the
Q93: Which role is responsible for defining and
Q94: Which of the following supports the PRINCE2
Q96: Which of the following is NOT a
Q97: Which document is used to record issues
Q98: If there is more than one version
Q99: Which role confirms stage and project progress