Multiple Choice
The table provides a project with the task lengths (in days) and precedence requirements, as well as the associated task costs, crashed time, and crash costs.
-It is desired to reduce the project completion time by 1 day. Based on the crash costs per day values, which task should be crashed first?
A) A
B) C
C) F
D) D
E) E
Correct Answer:

Verified
Correct Answer:
Verified