Multiple Choice
We may need to consider noncritical activities in estimating a project's overall duration if ______.
A) the noncritical activities have little slack time
B) the noncritical activities have a high variance
C) both A and B
D) neither A nor B
Correct Answer:

Verified
Correct Answer:
Verified