If a project is expected to be completed in 68 days with a project variance of 9 days,what is the probability that the project will be completed within 70 days?
A) about 45%
B) about 55%
C) about 65%
D) about 75%
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q47: We may need to consider noncritical activities
Q48: Which of the following is NOT one
Q49: The project's baseline _.<br>A)is the standard against
Q50: If the cost slope for an activity
Q51: If a project has an expected completion
Q53: Projections about how much the project will
Q54: The work breakdown structure identifies _.<br>A)each of
Q55: The Z value corresponding to a probability
Q56: If the most optimistic time for completing