Solved

If the Cost Slope for an Activity Is $10,000 Per

Question 50

Multiple Choice

If the cost slope for an activity is $10,000 per week,this means ______.


A) the activity will cost $10,000 for each week that it is accelerated
B) the primary firm will pay the contractor $10,000 for each week that the project is completed ahead of schedule
C) the contractor will have to pay the primary firm $10,000 for each week beyond the expected date of completion
D) the project leader will incur a penalty of $10,000 for each week that the project takes beyond expected date of completion

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions