Multiple Choice
If the cost slope for an activity is $10,000 per week,this means ______.
A) the activity will cost $10,000 for each week that it is accelerated
B) the primary firm will pay the contractor $10,000 for each week that the project is completed ahead of schedule
C) the contractor will have to pay the primary firm $10,000 for each week beyond the expected date of completion
D) the project leader will incur a penalty of $10,000 for each week that the project takes beyond expected date of completion
Correct Answer:

Verified
Correct Answer:
Verified
Q45: A project's variance is _.<br>A)the sum of
Q46: A project's standard deviation is _.<br>A)the square
Q47: We may need to consider noncritical activities
Q48: Which of the following is NOT one
Q49: The project's baseline _.<br>A)is the standard against
Q51: If a project has an expected completion
Q52: If a project is expected to be
Q53: Projections about how much the project will
Q54: The work breakdown structure identifies _.<br>A)each of
Q55: The Z value corresponding to a probability