A Project's Variance Is ______

Question 45

Multiple Choice

A project's variance is ______.


A) the sum of the variances of all of its critical activities
B) the average of the variances of all of its critical activities
C) the maximum of the variances of all of its critical activities
D) the minimum of the variances of all of its critical activities

Correct Answer: