Multiple Choice
Projections about how much the project will finally cost can be calculated based on ______.
A) the actual cost (AC) of the work performed to date and the earned value (EV) to date
B) the planned cost (PC) of the work performed to date
C) either A or B
D) neither A nor B
Correct Answer:

Verified
Correct Answer:
Verified