Solved

The Normal Activity Duration of Activity X Is 5 Weeks

Question 58

Multiple Choice

The normal activity duration of Activity X is 5 weeks and is budgeted to cost $12,000.The crash time for this activity is 3 weeks and is expected to cost $32,000.The cost slope for Activity X is ______.


A) $32,000 per week
B) $18,000 per week
C) $20,000 per week
D) $10,000 per week

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions