Multiple Choice
The normal activity duration of Activity X is 5 weeks and is budgeted to cost $12,000.The crash time for this activity is 3 weeks and is expected to cost $32,000.The cost slope for Activity X is ______.
A) $32,000 per week
B) $18,000 per week
C) $20,000 per week
D) $10,000 per week