Solved

If the Most Optimistic Time for Completing an Activity Is

Question 56

Multiple Choice

If the most optimistic time for completing an activity is 2,the most likely time is 4,and the most pessimistic time is 7,then the estimated time for the activity is ______.


A) 4.17
B) 10.58
C) 5.83
D) 6.42

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions